No Deskripsi Item Weight Factor (%) Duration (Day) Schedule Plan Plan (%) Actual (%)
Start Finish Last Week This Week Kumulatif Last Week This Week Kumulatif
1 Refurbish Tahap 1 100.00% 13 05/02/2024 18/02/2024 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
1.1 Pembersihan 8.00% 1 05/02/2024 06/02/2024 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
1.2 Pengelasan Tube Power Pack 23.00% 3 06/02/2024 09/02/2024 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
1.3 Pembuatan tampungan oli 8.00% 1 09/02/2024 10/02/2024 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
1.4 Penambahan Filter Oli 8.00% 1 10/02/2024 11/02/2024 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
1.5 Penggantian Piping System 15.00% 2 11/02/2024 13/02/2024 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
1.6 Penggantian Motor & Pompa 8.00% 1 13/02/2024 14/02/2024 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
1.7 Penggantian Flexible Hose 8.00% 1 14/02/2024 15/02/2024 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
1.8 Modifikasi Tangga 8.00% 1 15/02/2024 16/02/2024 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
1.9 Pengecatan 15.00% 2 16/02/2024 18/02/2024 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
2 Refurbish Tahap 2 Unit 2 100.00% 17 26/08/2026 12/09/2026 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
2.1 Rekondisi Sitem Control 35.00% 6 26/08/2026 01/09/2026 100.00% 0.00% 100.00% 50.00% 15.00% 65.00%
2.2 Perbaikan Piping Sistem 6.00% 1 01/09/2026 02/09/2026 100.00% 0.00% 100.00% 50.00% 5.00% 55.00%
2.3 Perubahan Desin Dudukan Sampson Post 6.00% 1 02/09/2026 03/09/2026 100.00% 0.00% 100.00% 50.00% 0.00% 50.00%
2.4 Pemasangan Pressure Gauge 6.00% 1 03/09/2026 04/09/2026 100.00% 0.00% 100.00% 50.00% 0.00% 50.00%
2.5 Pembuatan Cover Coupling Motor 6.00% 1 04/09/2026 05/09/2026 100.00% 0.00% 100.00% 50.00% 0.00% 50.00%
2.6 Pemasangan Drain House 6.00% 1 05/09/2026 06/09/2026 100.00% 0.00% 100.00% 50.00% 0.00% 50.00%
2.7 Pembuatan Atap Panel 6.00% 1 06/09/2026 07/09/2026 100.00% 0.00% 100.00% 50.00% 0.00% 50.00%
2.8 Pengecatan 12.00% 2 07/09/2026 09/09/2026 100.00% 0.00% 100.00% 100.00% 0.00% 100.00%
2.9 Function Test by QC IPK 12.00% 2 09/09/2026 11/09/2026 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2.10 FAT 6.00% 1 11/09/2026 12/09/2026 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%