List Material - HPU Unit 1

No Deskripsi Item Material Weight Factor (%) Schedule Plan Plan (%) Actual (%) Status Material
Start Finish Last Week This Week Kumulatif Last Week This Week Kumulatif PO Delivery Workshop
2 PROCUREMENT WORKS 100.00% - - - - - - - -
2.1 Tube OC 18.18% Sept. 1, 2026 Sept. 15, 2026 100.00% 0.00% 100.00% 100.00% 0.00% 100.00% YES YES YES
2.2 Plate Tubesheet 9.09% Sept. 1, 2026 Sept. 8, 2026 100.00% 0.00% 100.00% 100.00% 0.00% 100.00% YES YES YES
2.3 Plate Casing, Partition, Cap, Blind Flange, L Support 9.09% Sept. 1, 2026 Sept. 8, 2026 100.00% 0.00% 100.00% 100.00% 0.00% 100.00% YES YES YES
2.4 Pipe Nozzle, Flange, Level 9.09% Sept. 1, 2026 Sept. 8, 2026 100.00% 0.00% 100.00% 100.00% 0.00% 100.00% YES YES YES
2.5 Elbow 9.09% Sept. 1, 2026 Sept. 8, 2026 100.00% 0.00% 100.00% 100.00% 0.00% 100.00% YES YES YES
2.6 Coupling and Hex Plug 9.09% Sept. 1, 2026 Sept. 8, 2026 100.00% 0.00% 100.00% 100.00% 0.00% 100.00% YES YES YES
2.7 Base Valve, Tee Equal, Double Nipple, Tee Drat, Ball Valve, Hose Connection 18.18% Sept. 1, 2026 Sept. 15, 2026 100.00% 0.00% 100.00% 100.00% 0.00% 100.00% YES YES YES
2.8 Exhaust Fan 18.19% Sept. 1, 2026 Sept. 15, 2026 100.00% 0.00% 100.00% 100.00% 0.00% 100.00% YES YES YES