Installation Dedicated Fuel Gas Line from WK-01 to Fuel Header KJS
| WO Number | 3510008483 |
|---|---|
| PO Number | |
| Client | PT Medco E&P Rimau |
| PIC | Belum ditentukan |
| Status | DONE |
| Tanggal Kontrak | June 22, 2026 |
| Tahun Project | 2026 - 2026 |
| Tanggal Mulai | June 22, 2026 |
| Deadline | Oct. 3, 2026 |
| Description | Installation Dedicated Fuel Gas Line from WK-01 to Fuel Header KJS; Contract 3510008483; Plant PT Medco E&P Rimau; WPR No. 13, cut-off 21-Sep-2026. Approved summary reports plan 100%, actual 100%, re-baseline 100%, variance 0%. |
Overall Progress & S-Curve
Overall dihitung dari data progress yang tersimpan dan dapat diperbarui melalui admin.
Plan
Actual
Plan Cut Off
100.00%
Actual Cut Off
100.00%
Final Plan
100.00%
| Week | Date | Plan Weekly | Plan Cum. | Actual Weekly | Actual Cum. |
|---|---|---|---|---|---|
| 1 | 22 Jun 2026 | 0.00% | 0.00% | 0.00% | 0.00% |
| 2 | 29 Jun 2026 | 2.00% | 2.00% | 0.00% | 0.00% |
| 3 | 06 Jul 2026 | 6.00% | 8.00% | 2.00% | 2.00% |
| 4 | 13 Jul 2026 | 10.00% | 18.00% | 4.00% | 6.00% |
| 5 | 20 Jul 2026 | 9.00% | 27.00% | 6.00% | 12.00% |
| 6 | 27 Jul 2026 | 8.00% | 35.00% | 4.00% | 16.00% |
| 7 | 03 Aug 2026 | 9.00% | 44.00% | 3.00% | 19.00% |
| 8 | 10 Aug 2026 | 6.00% | 50.00% | 8.00% | 27.00% |
| 9 | 17 Aug 2026 | 8.00% | 58.00% | 14.00% | 41.00% |
| 10 | 24 Aug 2026 | 9.00% | 67.00% | 17.00% | 58.00% |
| 11 | 31 Aug 2026 | 7.00% | 74.00% | 12.00% | 70.00% |
| 12 | 07 Sep 2026 | 4.00% | 78.00% | 8.00% | 78.00% |
| 13 | 14 Sep 2026 | 12.00% | 90.00% | 20.00% | 98.00% |
| 14 | 21 Sep 2026 | 10.00% | 100.00% | 2.00% | 100.00% |
Man-Hours Curve
Plan dan actual man hours khusus project ini.
Plan Man Hours
Actual Man Hours